VSM guide / Symbols

Value stream mapping symbols

Every standard VSM symbol, drawn the way it appears on a map, with what it means and when to use it. All of them are in the free builder: drag them onto a map and the takt time, inventory days and lead time are calculated for you.

Draw with these symbolsStart from a template

Outside & control symbols

Outside & control

Customer

Who pulls the product. Sits top-right. Its data box holds the demand: pieces per month/day, packaging, shipping frequency.

Outside & control

Supplier

An outside source of material. Sits top-left. Note delivery frequency, lot size and lead time.

Outside & control

Production control

The scheduling department or system (MRP/ERP). Information arrows run from the customer to it and from it to the floor.

Process symbols

Process

Process box

One area where material flows continuously. A box ends wherever flow stops and inventory piles up. The data box underneath holds the measurements.

Process

Operator

A person. Shown inside process boxes by count; use this to call out a material handler or a shared operator.

Material symbols

Material

Inventory

Parts waiting between processes. Count them and note where they sit. Days = quantity ÷ daily demand; this drives the lead-time ladder.

Material

Order queue

Orders or jobs waiting at an office or planning step (an in-box). Enter part-equivalents so the timeline can turn it into days.

Material

Supermarket

A controlled stock with a fixed max. The downstream process takes what it needs; the upstream process makes only what was taken.

Material

FIFO lane

First-in-first-out lane with a maximum. When it is full the upstream process stops. Links two processes that can't flow continuously.

Material

Buffer / safety stock

Stock held to protect against demand swings (buffer) or internal problems (safety stock). Keep it visible and sized.

Material

Truck shipment

An external delivery. Write how often it comes or goes (e.g. "2× week") as its name.

Pull system symbols

Pull system

Production kanban

A card that authorizes a process to make a set quantity of a part.

Pull system

Withdrawal kanban

A card that tells a material handler to take a set quantity from a supermarket.

Pull system

Signal kanban

Triggers a batch when stock in a supermarket drops to a reorder point. Used for batch processes like stamping or molding.

Pull system

Kanban post

Where kanban cards are collected and held for pickup.

Pull system

Load leveling

A heijunka box that releases kanban in a mixed, even sequence to level both volume and mix at the pacemaker.

Pull system

Pull circle

Marks where a downstream process pulls from an upstream supermarket.

General symbols

General

Kaizen burst

An improvement needed to reach the future state. Put one at each spot where something has to change.

General

Go-see scheduling

Someone adjusts the schedule by walking the floor and looking at stock, rather than through the formal system.

General

Text note

Free text: schedules, notes, questions to follow up.

Flow arrows

Flow

Push arrow

Material made to a schedule and pushed to the next step, whether or not it needs it.

Flow

Shipment

Raw material arriving from a supplier, or finished goods leaving for the customer.

Flow

Pull / withdrawal

Material physically taken from a supermarket by the process that needs it.

Flow

Manual info

Information on paper or by word: printed schedules, ship lists, hot lists.

Flow

Electronic info

Information by EDI, email, MRP/ERP, a supplier portal.

Flow

Kanban path

The route kanban cards travel.

Flow

Rework loop

Parts sent back to an earlier step to be fixed.

Flow

Continuous flow

Parts move straight to the next step, one piece or one batch at a time, with no queue in between.

How to read a value stream map

Material flows left to right along the bottom: supplier, process boxes with inventory triangles between them, and finished goods shipped to the customer. Information flows right to left along the top: orders from the customer to production control, and schedules out to the processes. The timeline under the map compares the days parts spend waiting with the seconds or minutes they are worked on.

What is the difference between a push arrow and a withdrawal arrow?

A push arrow means a step makes parts to a schedule and pushes them to the next step whether it needs them or not. A withdrawal arrow means the next step pulls what it needs from a supermarket, usually with a kanban signal.

When should I use a FIFO lane instead of a supermarket?

Use a FIFO lane between steps that can't flow continuously but can process parts in order, with a maximum quantity. Use a supermarket when the upstream step serves several products or has long changeovers and must build to a small, controlled stock.

What does a kaizen burst mean?

A kaizen burst marks a place where an improvement is needed to reach the future state, such as cutting a changeover or adding a FIFO lane. Each one should become an action with an owner and a date.

Keep going